Additional information about the project: Customer:
|
Innowind (80 per cent owned by EDF EN) |
Project name: |
Chaba, Waainek and Grassridge |
Location/Country: |
Eastern Cape, South Africa |
Number of MW: |
105 MW |
Number of turbines/turbine type: |
35 V112-3.0 MW turbines |
Contract type: |
Turnkey/EPC |
Contract scope: |
The contract comprises supply, installation and commissioning of 35
V112-3.0 MW wind turbines, along with a VestasOnlineĀ® Business SCADA
solution, full scope civil and electrical works as well as a 10-year
full-scope service agreement (AOM 4000). |
Time of delivery: |
Delivery of the turbines for the three wind power plants is planned to
start mid-2014 and commissioning is expected to start in the third quarter
of 2014. |